Building the Dream at Karwick Village

At Karwick Village, every timber raised carries the hopes of our community. We’re not just building Karwick Village — we’re building futures.

Phase 1 of construction is underway, and with your support, we can keep framing an affordable, safe community for those who need them most.

Every dollar adds a roof, a window, a door — turning dreams into reality.

By helping us build this village, you’re creating places where families grow, friendships form, and belonging begins.

Donate today. Help us keep building Karwick Village.

Add Your Heading Text Here

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

Upcoming Events

Add Your Heading Text Here

Add Your Heading Text Here

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

Add Your Heading Text Here

Add Your Heading Text Here

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

Add Your Heading Text Here

Add Your Heading Text Here

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

Add Your Heading Text Here

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

Building Progress Updates

May 2025 - Footings Poured

Footings are poured for the first foundation! This is the first of four residential building foundations that will be going in this summer.

June 2025 - Foundation Poured

Foundation 1 is backfilled, and underground plumbing is being installed. 

IMG_0208

June 2025 - Plumbing Installed

Underground plumbing in 1st building complete. Slab will be poured as soon as inspections are complete.

IMG_0375 copy

Late June 2025 - Framing Started

Slab is ready, and framing is underway.  Major work to run the sewer down the center of the property is just getting started.